Grandhaven Elementary School

New $7 Million School with wood frame construction. The gym was block wall and steel roof system at the gym.

Facilitated RFI’s, submittals, shop drawings with the architect and owner. Was promoted to project manager 2/99. Managed the construction budget. Updated schedule on a monthly basis. Worked with owner and architect on change order approvals. Provided support to project superintendent on subcontractor disputes. Organized project closeout and coordinated getting the school personnel moved to the building in July.


 

[ click thumbnail for larger image ]


1999
McMinnville, Oregon

Client:
McMinnville School District